Mullumbimby ( NSW ) Telecommunications facility – MSB & SGP Upgrade

The Mullumbimby Project is a classic example of Ryan Wilks being able to cater to a customers needs.  The project entailed a detailed design of a 120/120/120 FRL generator room by Ryan Wilks to meet strict guidelines and site requirements.  With the replacement of the existing main switch board and the creation of a new Main Switch Room from an old storage closet, this proved Ryan Wilks’ experience and diversity within the building industry.

On the electrical side of the project, the replacement of the existing generating set with a new Cummins 75 KVA Set proved to be little challenge to the team as they stripped the room back to basics and started from the beginning.

The project was completed on time and under budget with 100% customer satisfaction upon handover.

Value $ 300k