Sydney City North/East CBD Data Centre – 550Kva UPS Installation
New 550Kva UPS to provide the electrical infrastructure to provide a high quality, ultra reliable fully serviced lettable space for high technology tenants on 6 existing levels. Works included construction of new rooms to house the UPS, batteries and air conditioning, upgrading of existing air conditioning on each of the 6 levels, harmonic filters on each of the existing 6 levels, new input and output switchboards including a 3200Kva static switch. New 3200amp busways to each of the 6 existing levels. Full load testing to 110% was carryout out prior to the strategic integration of the system into the existing UPS reticulation network.
Value $6.5 mil